Skip to Content

Honoring our past. Designing our future. Welcome to KCA’s new look.

HomeProjects

Lake Seminole Weir Replacement

Owner: Pinellas County, FL
Location: Pinellas County, FL
Construction workers using excavator by canal, adjusting concrete block
Lake Seminole
Grass-lined drainage area with water flowing over a weir, utility workers nearby
Lake Seminole
Man-made water channel with small waterfall and distant buildings across lake
Lake Seminole
Red construction crane lifting steel beams near water, two workers nearby
Lake Seminole
Water flowing over a curved dam into a lake under cloudy skies
Lake Seminole
Erosion near concrete wall by a calm lake with tall grass
Lake Seminole
Damaged concrete embankment with scattered debris, adjacent to a calm water body, flanked by parked trucks and grassy terrain
Lake Seminole
Calm lake with concrete banks and reflection of clouds
Lake Seminole
Rocky shoreline with rusted barriers along a calm lake under a blue sky
Lake Seminole
Worker in orange shirt using level on steel beam by water
Lake Seminole

The scope of work required at this Lake Seminole emergency response project in Pinellas County involves construction of a new temporary weir to restrict southern water flow from the lake through bridge culvert 150063 under Park Boulevard and thereby maintain the elevation of the lake. Failure of the existing weir, brought on by the impacts of Hurricane Helene, had resulted in unrestricted flow through the culvert that has been slowed but not eliminated by the exceptional emergency response of Pinellas County construction staff who placed numerous temporary 2’x2’x6’ concrete blocks and additional broken concrete riprap to temporarily obstruct the northern exterior openings of culvert. An improved and reliable method to control the lake elevation is currently in design and is planned for immediate installation. The temporary weir will be comprised of steel sheet piling, 50’ in vertical length, installed with a vibratory hammer supported by a crane working behind the shoreline. The worksite will be leveled in the vicinity of the crane usage for stability during its use. The top elevation of the proposed weir will match the elevation of the intact remnants of the existing weir. The new northernmost wall segment of the temporary weir will be installed parallel to the shoreline and approximately 10 feet north of the northernmost remnants of the existing damaged weir (at its approximate midpoint). Two new segments of sheet piling will extend from each end of the northern segment and taper outward back into the shoreline immediately beyond the wingwalls of the culvert. Floating turbidity barrier will encapsulate the worksite to minimize any buildup of silt from the installation. Once the emergency project is complete, the concrete blocks and riprap at the north end of the culvert will be removed and the leveled area on the shoreline will be restored and sodded. A permanent installation is currently being considered by the County and will be a separate project from this temporary emergency measure. Removal of the temporary sheet piling will occur upon the completion of the future permanent weir.

Focus Areas

  • Structures Design
  • Emergency Response
  • Bridge Inspection
  • Environmental Services

Recent Projects

Williams Road Southern Swale Analysis

Estero, FL

As part of the Willliams Road Improvements, KCA is assisting with drainage and stormwater analysis and maintenance of the southern swale along Williams Road from…

Williams Road Roundabout

Estero

KCA was selected by the Village of Estero to provide design and permitting services for the roadway and intersection improvements along Williams Road at Atlantic…

SR 679 (Pinellas Bayway) Structure E over Intracoastal Waterway, Design-Build (D/B)

Pinellas County, FL

As a partner to American Bridge Company and American Consulting Professionals, KCA was selected for the SR 679 (Pinellas Bayway) Structure E over the Intracoastal…